The loan agreement was signed in 2017 and Phase 1 commenced in January 2018. The Ministry is in Phase 3 of the CAF Project.
Under the CAF Project, priority is given to long connecting roads with heavy traffic volume and residential access. Key segments of the primary road network, including drainage, sidewalks, bridges, culverts, and safety features are being rehabilitated.
Roads under the CAF Project will be rehabilitated with two types of surfaces (i) asphalt or (ii) roller compacted concrete (RCC).
Roads | Status | Notes |
---|---|---|
Cane Garden to Bridgefield, St. Thomas | On-Going | Barbados Water Authority is conducting mains replacement |
Fustic Village, St. Lucy | Completed | Road widened and paved. |
Prior Park, St. James | On-Going | Barbados Water Authority recently completed mains replacement |
Rock Dundo, St. James to Gibbs, St. Peter - 2.1 km road | Phase 1 Completed | Barbados Water Authority has replaced and upgraded water mains along the main road and residential roads. |
Yorkshire Road, Christ Church | Phase 1 Completed | Barbados Water Authority has replaced old water mains with new ones. |
Temporary address:
2nd Floor
The Goddard Building
Haggatt Hall
St. Michael
Bridgetown, Barbados
PBX: 246-536-0000
psmtwm@barbados.gov.bb
information.unit@publicworks.gov.bb
Copyright © 2024 Ministry of Transport and Works | Barbados