ROAD WORKS ACTIVITIES FOR OCTOBER 21-25, 2024

Road Marking 

The road marking crews of the Ministry of Transport and Works (MTW) will repaint Top Rock Roundabout and Edwy Talma (Kendal Hill) Roundabout in Christ Church on the ABC Highway, and the Everton Weekes Roundabout in Warrens, St. Michael. Work will be done Monday to Thursday between 3:00 p.m. to 11:00 p.m., weather permitting.

Motorists are urged to avoid speeding through work areas while road markings are being done as this endangers the lives of workers and damages the freshly painted road markings.

Road Rehabilitation/ Road Construction

  • Airy Hill, St. George – paving
  • Animal Flower Cave Road, St. Lucy – suck well construction & deep milling
  • Babylon Road, St. Andrew – kerb construction
  • Bridgefield, St. Thomas – BWA works & design ongoing
  • Chance Hill, St. Lucy – box drain
  • Cherry Tree Hill, St. Andrew – preparations for road construction
  • Coggins Hill, St. Andrew – road closed due to excavation
  • Cottage Vale, St. Philip – excavation
  • Gibbons Terrace, Christ Church – box drain construction
  • Glenburnie, St. John – box drain & road base construction
  • Highway F, Bath, St. John – road base construction & building of box drain
  • Jemmotts Road, St. Lucy – kerb construction
  • King’s Street, St. Andrew – excavation & gabion installation
  • Laynes Bridge, St. Joseph – work on hold temporarily
  • Millionaire Road, St. Peter – accommodation works
  • Prior Park, St. James – kerb removal, excavation and setting out
  • Reece Road, St. Thomas – masonry work, suck well & box drain excavation
  • Rock Dundo, St. James to Gibbs, St. Peter – accommodation works
  • St. Simons, St. Andrew – reinforcement steel for box drain
  • Sweet Home Road, St. Peter – work on hold temporarily
  • Walkers Road, St. George – paving
  • White Hill Phase 2, St. Andrew – road and drainage construction

Drainage Works

  • Canal from Bridge Road to Globe Roundabout,, St. Michael
  • Castle Rock, Cane Garden, St. Thomas
  • Drain at Fontabelle close to Barvan Market, Mighty Grynner Highway, St. Michael
  • Garden Land, St.  Michael (continuing)
  • Halton Terrace, St. Philip
  • Headleys Land, St. Michael 
  • Lower Burney, Mapp Hill, St. Michael (in progress)
  • Rihanna Drive, St. Michael
  • St. Barnabas Heights, St. Michael (in progress)
  • Warrens Crescent, St. Thomas

Ongoing road works

St. Michael – Work on the footpath in Golden Rock, The Pine will be completed this week. Slabs have been cast, cured and will be put in place. Manhole covers repairs in Lightfoot Lane are on hold Work on the concrete slabs for Hastings is also on hold. The construction of a slipper and kerb and a new footpath at Long Gap continues with concrete to be poured shortly. Pothole patching is scheduled for districts.

St. John – Masonry works are ongoing at Malvern. De-bushing is scheduled for Bath Hill, Society Hill, Hothersal and the Bath Depot. Weeding is scheduled for Bath Hill .

St. Philip –  Construction of a bounce-up continues in Atlantic Park. In Ruby Tenantry and

Rock Hall, the construction of the slipper and kerb continues. Weeding is scheduled for Fortesque while debushing is planned for Fortesque, Heddings, Farm Road, Belair and Drakes Land. Pothole patching will be done in Rock  Hall and throughout the parish.

St. George – Milling will be completed in Airy Hill, while work continues on the short road in Constant Tenantry under the Community Access Road Transformation (CART) Project. Drainage work will be carried out in Walkers; pothole patching is due for Valley Vista, St. Judes, Ellesmere and Ellerton; weeding and de-bushing are scheduled for Bridgecot South, Lower Newbury and Workmans.

Christ Church – Concrete works are scheduled for Gibbons Terrace, Sheraton Park and Homestead Circle. Drainage work is being carried out on Maxwell Main Road. Pothole patching is scheduled for Bannatyne, St Davids, Edey’s Village and Kingsland Gardens. Debushing will be also carried out at Sayers Court, St. Christopher and Silver Sands. Due to road depressions at Sayers Court, motorists, especially drivers of heavy-duty vehicles, are urged to be cautious while travelling around the small roundabout.

St. Joseph/St. Andrew – Road repairs to commence at Mellows. Installation of hand rails and preparation for paving of temporary road at Swanns. Persons are reminded not to drive on Swanns Bridge which has been closed due to deterioration. The road is being reinstated at St. Elizabeth Road following repairs to a culvert. Gabion work is also expected to commence in St. Elizabeth. The road at Trio Path is being reinstated and preparations are being made to pave it. In Newton Crescent, a section of the road will be oiled and rolled. Manual and mechanical debushing will take place from Cox Hill to Gaggs Hill, the junction of Turner’s Hall to Swanns and Bawdens, Sailor Gully to Indian Ground to Welchtown, The Ridge to Springfield and Russia Gully. Extensive pothole patching will take place from Cherry Tree Hill to Morgan Lewis Windmill.

St. Lucy – Work continues on Pie Corner Bridge; the road is closed until further notice. Motorists may divert at Well Road; local access will be granted. The second half of paving  is still to be completed at Maycocks and Date Tree Hill. Work on Well Road No. 2 is soon to be completed under the C.A.R.T Programme. Pot-hole patching and debushing will be done throughout districts.

St. Peter – In Round-de-Town, a drive enterance/culvert; slipper and kerb and manhole repairs will soon to be completed. Pothole patching is being done throughout the parish. Warleigh Road will also be patched. Farm Bridge remains closed until further notice; access to the Ronald Mapp Highway from Speightstown, and vice versa, is through Warleigh Road. 

St. James – Manhole covers are being repaired along Highway 1 in  Porters and Holetown. Drainage work is scheduled for Trents and Haynesville. Headwall construction to commence in Durants.Tree trimming will be done in Holders Hill and mechanical debushing will continue from Lancaster to Trents. Pothole patching is scheduled throughout the districts.

St. Thomas – Drainage work and preparations are being made for paving in Stoney Gully. Extensive pothole patching is being carried out in Airy Cot, Hangman Hill and Canefield. De-bushing is scheduled for various districts.

MTW advises pedestrians and motorists to obey traffic wardens, pay attention to signage, and exercise due care and attention when traversing work sites.