Road rehabilitation of Lodge Hill, St. Michael starts this Friday night

Lodge Hill in St. Michael will undergo road rehabilitation for approximately four weeks starting Friday, July 25, 2025, from 8:30 p.m. to 6:00 a.m. nightly. B&R Infrastructure Ltd., the contractor working on behalf of the Ministry of Transport and Works (MTW), will deep mill the roadway, excavate some sections, construct kerbs, clean suck wells and […]
ROAD WORKS ACTIVITIES FOR JULY 21 – 25, 2025

Road Marking The Road Marking crew of the Ministry of Transport and Works (MTW) will repaint the traffic lights junction at Eagle Hall as well as the traffic lights junction at Baxters Road, St. Michael. The crew will also remark BET Hill to the Samuel Jackman Prescod Institute (SJPI) Roundabout heading south. Work will be […]
Road Rehabilitation of Bank Hall Cross Road, St. Michael: Lower Bank Hall traffic lights to traffic lights junction at Eastmond Corner

The Ministry of Transport and Works (MTW) will carry out road rehabilitation on Bank Hall Cross Road in St. Michael from the Lower Bank Hall Traffic Lights to the traffic lights junction at Station Hill/Eastmond Corner under its Focused Roads Programme. On Monday, July 21, 2025, Infra Construction Inc. will begin road works, which will […]
Road Works Activities for July 7 to 11, 2025

Road Rehabilitation/ Road Construction Drain Cleaning Ongoing road works St. Michael – Work on the medium and slipper on the Mighty Grynner Highway continues, and clean-up of the area is to be completed this week. Manhole repairs and excavation also continue on the Mighty Grynner Highway. Repairs to a head wall in Martindales Road and […]
PAVING SCHEDULED FOR FOUL BAY, ST. PHILIP AND PHILIPS ROAD, ST. JOSEPH

The Paving Unit of the Ministry of Transport and Works (MTW) will resurface Foul Bay, St. Philip while C. O Williams Construction Ltd. will carry out work on Philips Road in St. Joseph, in a continued effort to further improve road conditions across the island. Starting Monday, July 7, 2025, Infra Construction Inc. will begin […]
Change of Scope of Works: 1st and 2nd Avenue Rouen Road, off of Rouen Road, My Lords Hill, St. Michael

Work on 1st and 2nd Avenues Rouen Road, off Rouen Road, My Lords Hill, St. Michael, commenced on Friday, June 6, 2025, under the Ministry of Transport and Works (MTW) Focus Road Works programme. The original scope of work involved milling the existing road surface to a depth of 50mm and repaving, with an estimated […]
ROAD REHABILITATION ON HIGHWAY C, ALONG ORANGE HILL, ST. JAMES, PROGRESSING STEADILY

Road rehabilitation along Highway C in Orange Hill in St. James is progressing steadily since work commenced in April this year, under the Ministry of Transport and Works (MTW) Scotland District Road Rehabilitation Programme. Work is being carried out in phases, and is executed by the China National Complete Plant Import and Export Corporation (COMPLANT) […]
Road Works Activities For June 23 – 27, 2025

Road Marking The Road Marking crew of the Ministry of Transport and Works (MTW) will complete the remarking of the newly paved section of the D’Arcy Scott Roundabout to the Welches Roundabout, following a delay. Reflective studs (cat eyes) will also be installed. The northbound and southbound lanes from the bottom of BET Hill to […]
UPDATE ON THE PROGRESS OF WORK AT PRIOR PARK ST. JAMES

The Ministry of Transport and Works (MTW) is advising residents and road users that roadworks at Prior Park, St. James are expected to be completed by the end of August this year, barring adverse weather conditions or unforeseen circumstances. The project, which began in September 2024, was not without challenges. Deep excavation had to be […]
2ND PHASE OF WILDEY TRIANGLE PAVED UNDER HIGHWAY MAINTENANCE PROGRAMME

Phase 2 of the rehabilitation of the Wildey Triangle, located along the ABC Highway in St. Michael, has been completely paved. Executed under the Ministry of Transport and Works’ (MTW) Highway Maintenance Programme, in collaboration with contractor C.O. Williams Construction Ltd., this phase experienced periodic closures due to a few delays. These delays were primarily […]