RENEWABLE ENERGY INSTALLATIONS

GEED also facilitates electrical inspections for Renewable Energy installations.

The following documents must be submitted

  • Application for inspection of an electrical installation

  • One single-line diagram outlining the components of the systems, the cable sizes used, and the rating of the protection device incorporated in the design

  • Specification sheets of the Inverters, Batteries, and PV Panels

To apply for an electrical inspection for a Renewable Energy installation, download the form or click here https://forms.gov.bb/Electrical_Installation_Application

Forms can also be collected from the GEED’s front desk at Verona House, Bank Hall, St. Michael. Please note that the application can only be facilitated by a licensed electrician. 

Cost of an Inspection

Payment

Inspection fees are paid at the Cashier’s window, Ministry of Transport and Works, Pine East-West Boulevard, The Pine, St. Michael. Completed forms should be submitted at the same time payment is made.