Road Marking
The Road Marking crew of the Ministry of Transport and Works (MTW) will paint school pedestrian crossings on Highway 7. They will also repaint road markings from the Deighton Griffith Secondary School to the Edwy Talma Roundabout, as well as from Top Rock to the Errol Barrow (Graeme Hall) Roundabout. Work will be done on Tuesday and Wednesday of this week, between 6:00 p.m. and 4:00 a.m., weather permitting.
Motorists are urged to avoid speeding through work areas while road markings are being done as this endangers the lives of workers and damages the freshly painted road markings.
Road Rehabilitation/ Road Construction
- Airy Hill, St. Joseph – culvert construction
- Babylon Road, St. Andrew – drainage & roadbase construction
- Bruce Vale Bridge – bridge demolition completed; surveying & gabion works
- Chance Hill, St. Lucy – kerb and culvert construction
- Coggins Hill, St. Andrew – stub wall, culvert & drainage construction
- Cottage Vale, St. Philip – roller compacted concrete (RCC)
- D’Arcy Scott Roundabout to Welches Roundabout, St. Michael – milling & paving
- Eckstein Village, St. Michael – accommodation works
- Glenburine Road, St. John – gabion construction
- Grant’s Gap, Westbury Road, St. Michael – milling & paving
- Highway B2/Cherry Tree Hill, St. Andrew – drainage & gabion construction
- Highway D: Content to Dukes, St. Thomas – road reconstruction
- Hangman Hill to Bridgefield, St. Thomas – road reconstruction; section closed
- Highway F Phase 1, St. John – paving & road construction
- Huntes Road, Carrington Village, St. Michael – milling & paving
- King’s Street, St. Andrew – gabion foundation backfilling
- Laynes Bridge, St. Joseph – culvert construction
- Link Road/Four Hill, St. Peter – suckwell construction
- Mose Bottom, St. Andrew – drainage construction
- Park Road – 1st, 2nd, 3rd Avenues, St. Michael – concrete works, milling & paving
- Prior Park, St. James – road reconstruction
- Reece Road, St. Thomas – drainage construction
- St. Margaret’s, St. John – kerb and culvert construction
- Sunflower Drive, Cane Garden, St. Michael – milling & paving
- White Hill Phase 2, St. Andrew – gabion construction
- Wildey Triangle, St. Michael – road rehabilitation/milling & paving
- Yearwood Road, St. Joseph – milling & paving
Drain Cleaning
- 2nd Ave Cane Garden, St. Thomas
- 5th Ave Holders Hill, St. Michael
- ABC Highway going East
- Black Rock, St. Michael
- Date Tree Hill, St. Peter
- Durants Corner, Christ Church
- Elizabeth Park, Christ Church
- James Street, Bridgetown
- Lr Collymore Rock, St. Michael
- Mount Standfast, St. James
- Paynes Bay, St.James
- Taitt Hill, St. George
- Tudor Street, Bridgetown

Ongoing road works
St. Michael –Excavation is due to start to facilitate building of an additional 20 feet of slipper and kerb at Sargeants Village. Manhole repairs and excavation will start on the Mighty Grynner Highway. Work continues on the manhole at Crumpton Street. Repairs to the slipper and kerb at Tweedside Road and the reconstruction of the footpath at Bridge Road are completed. Pothole patching is scheduled throughout the parish.
Christ Church – Repairs to footpath and manhole covers on footpath near Southern Plaza entrance. In Gibbons Terrace, masonry work continues on the newly built drain while repairs to road edges and curbs also continue. Drainage work continues in Harmoney Hall. Pothole patching is scheduled for Kingsland, Homestead, Wilcox, Inch Marlow, Sayes Court, Plumgrove, Elizabeth Park, St. David’s, Briar Hall, Warners, Charnocks and Ealing Park.
St. George – Preparation for road surfacing will be carried out on Valley Main Road. Weeding will be done in Rowans Park, while debushing will be done in Boarded Hall. Drainage work to be done in Lower Estate and Carmichael Junction.
St. Lucy – Masonary work is scheduled for Mount View. Drain cleaning will be done along Charles Duncan O’Neal Highway (Checker Hall). Pothole patching is scheduled throughout the district.
St. Peter – Repairs continue to the slipper and kerb on Maynards Retreat Road. Masonary work is scheduled for the junction of Tom Bend Road and Ashton Hall Main Road. Debushing will be done in Maynards Ridge and along Highway 1 – Ashton Hall Main Road. Farm Bridge remains closed until further notice; access to the Ronald Mapp Highway from Speightstown, and vice versa, is through Warleigh Road.
St. James – Repairs to manhole covers continue along Highway 1 – while at Road View bollards will be installed at Oxnards Main Road.
St. John – Masonry works continue in Small Town and a kerb wall will be reconstructed at Cottage. Weeding will be carried out on Society Hill and debushing in Bath Hill, Malvern and Clifton Hall. Pothole patching will be carried out throughout the parish.
St. Philip – Construction of a haunch and slipper continues in Atlantic Park. The reconstruction of slipper and kerb continues in Farm Road. Kerb reconstruction is ongoing in Ruby Tenantry. Manual weeding will be done in Ruby Development and Duncans, while mechanical debushing will be done in Chapel.
St. Thomas – Plastering of the retaining wall at Stoney Gully continues. Debushing, drainage work, and pothole patching are scheduled throughout districts.
St. Joseph/St. Andrew – Construction of slipper and curb at Lakes Village The construction of a box drain and walk over continues for Bathsheba Park. Road construction is ongoing at Swanns, while slipper and kerb continues to be built at Jackmans Alley, Orange Hill. Debushing, patching and drainage work are scheduled for throughout the parishes. Persons are reminded not to drive on Swanns Bridge which has been closed due to deterioration.