Road Marking
The road marking crew of the Ministry of Transport and Works (MTW) will repaint road markings and install reflective studs along the Ronald Mapp Highway from Redmans Village to Westmoreland. Pedestrian crossings will continue to be remarked along Black Rock. Work will be done Monday to Thursday between 3:00 p.m. and 11:00 p.m., weather permitting.
Motorists are urged to avoid speeding through work areas while road markings are being done as this endangers the lives of workers and damages the freshly painted road markings.
Road Rehabilitation/ Road Construction
- Animal Flower Cave Road, St. Lucy – drainage works
- Babylon Road, St. Andrew – Lego retaining wall, kerb and drainage construction
- Bruce Vale Bridge – bridge demolition completed; gabion works
- Chance Hill, St. Lucy – drainage construction
- Chelston Avenue, St. Michael – kerb construction
- Coggins Hill, St. Andrew – Slipper and kerb & drainage construction
- Cottage Vale, St. Philip – excavation
- Eden Lodge Avenue, St. Michael – concrete works, milling and paving
- Glenburnie, St. John – base course construction
- Highway B2/Cherry Tree Hill, St. Andrew – (road closed) gabion repair
- Highway D, Content to Dukes, St. Thomas– road reconstruction (excavation)
- Highway F (Phase 1), St. John – drainage and retaining wall construction
- Highway R, Fort George Heights to Edey Village – pothole patching
- Jemmotts Road, St. Lucy – road base and culvert construction
- Jessamine Road, St. Michael – milling and paving
- King’s Street, St. Andrew – gabion and rip rap construction
- Laynes Bridge, St. Joseph – gabion construction
- Link Road & Four Hill, St Peter –drainage construction
- Mose Bottom, St. Andrew – retaining wall and drainage construction
- Park Road – 1st, 2nd, 3rd Avenues, St. Michael – concrete works, milling & paving
- Prior Park, St. James – excavation
- Reece Road, St. Thomas – kerb and drainage construction
- Rock Dundo, St. James to Gibbs, St. Peter – kerb construction
- St. Elizabeth’s Village – gabion construction
- St. Margaret’s – excavation of BWA trenches
- White Hill Phase 2, St. Andrew – gabion construction
Drain Cleaning
- Advent Aveue, Bank Hall, St. Michael
- Ashdeane Village, Black Rock, St. Michael
- Flat Rock, St. George (in progress)
- Fortescue, St. Philip
- Grazettes Primary School, Grazettes, St. Michael
- Old Chancery Lane, Christ Church
- Pegwell Boggs, Christ Church (in progress)
- Sealy Land, Bank Hall, St. Michael
- Tamarind Avenue to Pinders Avenue, Culloden Road, St. Michael
Highway Beautification Programme (Debushing)
- St Lucy: Crab Hill to Alexandra
- St. Peter: Highway 2: Farley Hill to St. Andrew Parish Church; The Risk
- St. Andrew: Babylon Road to Rock Hall (St. Peter) via Bawdens
- St Thomas: Highway 2: Cane Garden to Belleplaine via Bridgefield, Hopewell, Welchman Hall; Content Road
- St. John: Highway 3: St Elizabeth to Blades Hill
- St. Joseph: Melvins Hill through Parks/Saddleback/Coconut Grove to Springfield Road
- St. Philip: Highway O: Rices to Sterling
- St. George: Highway 4B: The Glebe to the Junction at Carmichael Road; Newbury/St. Judes to Todds Land; Highway 4: Salters to Drax Hall
- St. James: Sea View Road
- St. Michael: Jemmotts Lane, Martindales Road, Halls Road, Country Road, Passage Road and Westbury Road; Harmony Hall, Station Hill, Waterford, Hothersal Turning, Lower Estate; Baxters Road, Barbarees Hill, Tudor Bridge, Spooners Hill, Green Hill and Canewood Road
- Christ Church: Highway Q: Newton to Windsor; Enterprise Road; Highway U: Thornbury Hill to Chancery Lane

Ongoing road works
St. Michael – The work at Forde’s Road was completed; only clean up remains to be done. Slipper and kerb will be started at Sargeants Village to channel the flow of water. Manhole repairs continue at the traffic lights adjoining Roebuck Street and Crumpton Street; excavation is finished and masonry work will start next. Excavation continues for a footpath at Bridge Road. Pothole patching throughout the district.
Christ Church – Masonry works on slipper and kerb continue at Seaside Drive in Atlantic Shores; resurfacing is also on the schedule. Kerb construction and resurfacing will be done in Gibbons Terrace. Repairs are scheduled to start on a headwall on Cane Vale main road. Drainage work will be done in Lowlands and Chancery Lane. Pothole patching is scheduled for Thyme Bottom, Silver Hill, Atlantic Shores, Plumgrove, Edey Village and other districts.
St. George – Masonry work continues in Fairview, and will commence in Superlative. Weeding will be done at Middleton, Sweet Vale, and Thorpes Cottage. Debushing will be carried out in the Mount. Drainage is scheduled for Charles Rowe Bridge. Patching is scheduled for Applewhaites, Jericho, Sweet Vale and Walkers.
St. Lucy – Work continues on Pie Corner Bridge; Slipper and kerb as well as headwalls are scheduled to be repaired in Josey Hill. Slab work is ongoing in Alleynedale. Well cover repairs are being carried out from Alleynedale to Archers Bay. Pothole patching will be conducted throughout districts.
St. Peter – Manhole construction is ongoing in Upper Castle. Masonry and drainage works are ongoing in Speightstown. Roadworks is oingoing for Tom Bend Road. Farm Bridge remains closed until further notice; access to the Ronald Mapp Highway from Speightstown, and vice versa, is through Warleigh Road.
St. James – Repairs are ongoing to manhole covers along Highway 1 from Porters, St. James to Mullins, St. Peter. Pothole patching is scheduled for several districts.
St. Philip – Construction of a bounce-up as well as slipper and kerb continues in Atlantic Park. The reconstruction of slipper and kerb is ongoing at Ruby Village Road and Farm Road. Manhole repairs are scheduled for Industry Hall, while manhole reinstatement is scheduled for Lucas Street. Mechanical debushing will be carried out at Rockhall, Pounder Road, Jezreel and weeding will be done in Union Development.
St. John – Weeding in College Land continues and debushing is scheduled for Kendal. Pothole patching will be carried out in Martin’s Bay and throughout the parish. Masonary works in Coach Hill have been completed.
St. Thomas – Construction of a connecting footpath and retaining wall continue at Stoney Gully. Debushing, drainage work and pothole patching are scheduled throughout districts.
St. Joseph/St. Andrew – Retaining wall and gabion construction as well as roadworks are ongoing at St. Elizabeth. Preparations on road paving is scheduled for Swanns. Pothole patching, drain cleaning and debushing are slated for both parishes. Persons are reminded not to drive on Swanns Bridge which has been closed due to deterioration.