Road Marking
The road marking crew of the Ministry of Transport and Works (MTW) will continue repainting pedestrian crossings on Highway 1. Reflective studs will be installed and road markings repainted along the KNR Husbands Highway and in Speightstown. Work will be done Monday to Thursday between 3:00 p.m. and 11:00 p.m., weather permitting.
Motorists are urged to avoid speeding through work areas while road markings are being done as this endangers the lives of workers and damages the freshly painted road markings.
Road Rehabilitation/ Road Construction
- Animal Flower Cave Road, St. Lucy – drainage works
- Babylon Road, St. Andrew – kerb construction and building of Lego retaining wall
- Boarded Hill to Stephney, St. George – milling and backfilling
- Bridgefield, St. Thomas – designs ongoing
- Bruce Vale Bridge – demolition completed; gabion works
- Chance Hill, St. Lucy – drainage construction
- Coggins Hill, St. Andrew – Slipper and kerb & drainage construction
- Cottage Vale, St. Philip – cadastral surveys ongoing
- Glenburnie, St. John – base course construction
- Highway 1B/Cherry Tree Hill, St. Andrew – (road closed) preparations for road construction
- Highway D, St. Thomas– road reconstruction (excavation)
- Highway F (Phase 1), St. John – drainage, retaining wall & road base construction
- Jemmotts Road, St. Lucy – road base and culvert construction
- King’s Street, St. Andrew – gabion and rip rap construction
- Laynes Bridge, St. Joseph – culvert & backfilling of gabions
- Link Road & Four Hill, St Peter – drainage construction
- Mose Bottom, St. Andrew – drainage construction
- Prior Park, St. James – excavation & paving
- Reece Road, St. Thomas – road base construction
- Rock Dundo, St. James to Gibbs, St. Peter – paving
- St. Elizabeth’s Village – gabion construction
- St. Margaret’s – excavation of BWA trenches
- White Hill Phase 2, St. Andrew – gabion construction
Drain Cleaning
- Ashdeane Village, Black Rock, St. Michael (in progress)
- Fortescue, St. Philip
- Goodland Gardens, Christ Church
- Lyders Hill, St. Philip
- Old Chancery Lane, Christ Church
- Pegwell Boggs, Christ Church
- Sealy Land, Bank Hall, St. Michael
- Upper Carters Gap, Christ Church
Highway Beautification Programme (Debushing)
St Lucy: Charles Duncan Oneal Hwy from its junction with Hwy 1B at Checker Hall to its junction with Hwy B in Pleasant Hall
St. Peter: Mount Brevitor via French Village to Indian Ground
St. Andrew: Plum Tree Road
St Thomas: Content Rd, Hwy D; Dunscombe to Cane Garden; Hwy 2 from Hopewell to Welchman Hall
St. John: Hwy 3 from St Elizabeth to Blades Hill; Hwy 4 from Stewart Hill to Kendal
St. Joseph: Hwy 3A from Sugar Hill to Bruce Vale; Blackmans to Horse Hill via Highway 3D and Hwy 3E
St. Philip: Hwy N Oldbury to Long Bay via Rices, Crane, and Belair
St. George: Hwy 5 Salters to Six Roads; Hwy 4 from Salters to Drax Hall
St. Micael: Coleridge Street, White Park Road, Lower and Upper Bank Hall Main Road; Grazettes Main Road
Christ Church: Hwy 6, Newton to Six Roads; Dayrells Road and Golf Club Road; Hwy 7 from Rendezvous Road to the Tom Adams Roundabout
St. James: Carlton Road from Hwy 1 to Ronald Mapp Hwy; Husbands Main Road, Thorpes Main Road, Holders Main Road

Ongoing road works
St. Michael – A headwall is being constructed in Forde’s Road; formwork has been erected and concrete will be poured. Excavation to repair a manhole at Roebuck Street as well as to repair a footpath at Bridge Road are scheduled. Pothole patching throughout the district.
St. Philip – Construction of a bounce-up as well as slipper and kerb continues in Atlantic Park. The rehabilitation of slipper and kerb at Ruby Tenantry Road is ongoing. Manhole reinstatement is due at Lucas Street. Mechanical debushing will be carried out at Four Roads, Rock Hall, Ruby Development and Union Development. Manual weeding will be done in Vineyard, while pothole patching is scheduled for various districts.
St. George – Masonry work is being done along Fairview and possibly Carmichael junction. Weeding will continue in Middleton and Thorpes Cottage, while mechanical debushing will be done along Paradise.
Christ Church – Drainage work will be done in Chancery Lane, Ealing Park and Oistins. Debushing will be carried out in Silver Sands and Carters Gap. Repairs to the slipper and kerb continue in Gibbons Terrace, while a headwall will be started along Cane Vale main road. Repairs to the kerb and resurfacing are due at Seaside Drive in Atlantic Shores. Pothole patching is scheduled for Silver Hill Main Road, Plumgrove, Coverley, Thyme Bottom, Parish Land, Coral Ridge, Cane Vale main road, Sunrise Avenue in Atlantic Shores, St. Davis, Fairy Valley and a section of the ABC Highway.
St. Thomas – Construction of a connecting footpath and retaining wall continue at Stoney Gully. Debushing, drainage work and pothole patching are scheduled throughout districts.
St. Joseph/St. Andrew – Retaining wall and gabion construction as well as roadworks are ongoing at St. Elizabeth. Preparations on road paving is scheduled for Swanns. Pothole patching, drain cleaning and debushing are slated for both parishes. Persons are reminded not to drive on Swanns Bridge which has been closed due to deterioration.
St. Lucy – Work continues on Pie Corner Bridge; Debushing is due in Maycocks. Slab work is ongoing in Alleynedale. Well cover repairs will be carried out from Alleynedale to Archers Bay. Pothole patching will be carried out in Maycocks, Friendly Hall, Nestfield to Spring Hall, Friendship, Mount Gay, Bishops, Coconut Hall, River Bay, Hope Road, Half Acre to Chance Hall, and Clinketts.
St. Peter – Manhole construction is ongoing in Upper Castle. Slipper and kerb construction is scheduled for Tom Bend Road, while masonry and drainage works are slated for Speightstown. Pothole patching will be done throughout the districts including Maynards, Round the Town, Portland to Boscobelle, Mount Brevitor and others. Farm Bridge remains closed until further notice; access to the Ronald Mapp Highway from Speightstown, and vice versa, is through Warleigh Road.
St. James – Repairs to manhole covers along Highway 1. Pothole patching is scheduled for Husbands Main Road (near Queen’s College), Highway 1 from The Garden to Weston, The Whim, Haynesville Housing Area, Road off Holders Hill, Watermans Village, 1st Ave Upper Carlton, Doughlin Road Lower Carlton, Greaves Road, Westmoreland Road, Risk Road in Fitts Village.
St. John – Manhole repairs in Edgecliff. Weeding in College Land continues, and pothole patching will be done throughout the parish. Masonary works in Coach Hill have been completed.
Friday, January 31, 2025
Information Unit
MTW