ROAD WORKS ACTIVITIES FOR JANUARY 6-10, 2025

Road Marking 

The road marking crews of the Ministry of Transport and Works (MTW) will repaint and install reflective studs along the Ronald Mapp Highway to St. Lucy Parish Church. Work will be done Monday to Thursday between 3:00 p.m. and 11:00 p.m., weather permitting.

Motorists are urged to avoid speeding through work areas while road markings are being done as this endangers the lives of workers and damages the freshly painted road markings.

Road Rehabilitation/ Road Construction

  • Babylon Road, St. Andrew – box drains and kerb & slipper construction
  • Bridgefield, St. Thomas – BWA works & design ongoing
  • Chance Hill, St. Lucy – box drain construction
  • Highway 1B/Cherry Tree Hill, St. Andrew – (road closed) preparations for road construction
  • Coggins Hill, St. Andrew – restricted access
  • Cottage Vale, St. Philip – cadastral surveys ongoing
  • Glenburnie, St. John – box drain & road base construction
  • Highway F, Bath, St. John – paving; road closed
  • Jemmotts Road, St. Lucy – BWA works ongoing
  • King’s Street, St. Andrew – gabion works
  • Laynes Bridge, St. Joseph – gabion works and culvert construction
  • Prior Park, St. James – sections of road to be paved
  • Reece Road, St. Thomas – masonry work, suck well & box drain excavation
  • Rock Dundo, St. James to Gibbs, St. Peter – kerb construction, work ongoing
  • St. Simons, St. Andrew – box drain continues
  • Sweet Home Road, St. Peter – on hold temporarily
  • White Hill Phase 2, St. Andrew – road and drainage construction

Drain Cleaning

  • Fortesque, St. Philip 
  • Kingsland Terrace, Christ Church 
  • St. Hill Road, Carrington Village, St. Michael
  • Wynter Crawford (Six Roads) Roundabout, St. Philip

Highway Beautification Programme (Debushing)

St Lucy:          Highway 1B from Colleton to Bishops

St. Andrew:    Highway B: Junction with Ermie Bourne Highway to Canefield Road

St. Joseph:       Blackman’s to Horse Hill via Highway 3D and Highway 3E

St. Philip:        Highway 5B Apple Hall to Blades Hill

St George:       Highway 4 from Salters to Drax Hall, Highway 5 Salters to Six Roads

St. Michael:     Baxters Road, Barbarees Hill, Tudor Bridge, Spooners Hill, Green Hill and Canewood Road, Jemmotts Lane, Martindales Road, Halls Road, Country Road, Passage Road and Westbury Road

St James:         St Stephen’s Hill from Black Rock Main Road to Cave Hill Road, Black Rock Road, Eagle Hall

Ongoing road works

Christ Church – Kendal Hill and Gall Hill junction – manhole repairs Concrete works continue at Gibbons Terrace. Drainage work is scheduled for St. Lawrence Gap while debushing will be carried out in Carter’s Gap. Pothole patching throughout the district. Due to road depressions at Sayes Court, motorists, especially drivers of heavy-duty vehicles, are urged to be cautious while travelling around the small roundabout.

St. Philip –  Construction of a bounce-up continues in Atlantic Park. The construction of  slipper and kerb also continues at Ruby Plantation Road while a manhole is being repaired in Lucas Street. Weeding is scheduled for Vineyard.

St. Michael –Repairs to footpaths on Brittons New Road to Dalkeith continues. The sidewalks are also being repaired at the junction of Pine Plantation Road and Walmer Lodge. Concrete slabs are being cast for the sidewalk along Collymore Rock. Work is on hold at King William Street and at Lightfoot Lane in The City.

St. John – Tenantry road repairs at Malvern while masonry works are ongoing at Cherry Grove/Henley. Mechanical debushing will be done at Sargeants Street.

St. George – Work continues on the short roads in Constant Tenantry under the Community Access Road Transformation (CART) Project. Masonry work is being done at the Valley Main Road. Drainage work will be carried out on Ellerton Main Road.

St. Joseph/St. Andrew – Gabion work at St. Elizabeth to be completed this week Road repairs continue at Spa Hill. Persons are reminded not to drive on Swanns Bridge which has been closed due to deterioration. Road works at Trio Path and Upper Parks.

St. Lucy – Work continues on Pie Corner Bridge; the road is closed until further notice. Motorists may divert at Well Road; local access will be granted. Work on Well Road No. 2 is soon to be completed under the C.A.R.T Programme. Debushing will be carried out throughout the district.

St. Peter – Manhole to be repaired in The Castle. Debushing at Portland to Farley Hill. Farm Bridge remains closed until further notice; access to the Ronald Mapp Highway from Speightstown, and vice versa, is through Warleigh Road.  Portland to Farley hill man

St. James – Repairs to manhole covers along Highway 1 in  Porters and Holetown have been completed as well as the drainage work at Hoytes Village.

St. Thomas – Preparations are being made for paving in Stoney Gully. Debushing is scheduled throughout districts.