NOTICES

ROAD WORKS ACTIVITIES FOR March 24 – 28, 2025

A section of Glenburnie, St. John was recently paved.

Road Marking 

The Ministry of Transport and Works (MTW) road marking crew will repaint centre lines from the traffic lights on Pine Plantation Road to the Collymore Rock junction in St. Michael, as well as Lower Estate to Applewaites, St. George. A crew will also remark, with centre lines and install reflective studs (cat eyes), along the Carmichael junction to Constant; Constant roundabout to Dash Valley, and Dash Valley to Hanson Hill (Highway 5). Work will be done Monday to Thursday between 6:00 p.m. and 4:00 a.m., weather permitting.

Motorists are urged to avoid speeding through work areas while road markings are being done as this endangers the lives of workers and damages the freshly painted road markings.

Road Rehabilitation/ Road Construction

  • Airy Hill, St. Joseph – road repairs, realignment and gabion work (road closed)
  • 4th Avenue Reece Road, Brittons Hill,  St. Michael – milling and paving
  • ABC Highway from Highway R (BET Hill) to SJPI Roundabout (northbound lanes) – paving
  • Animal Flower Cave Road, St. Lucy – drainage works
  • Babylon Road, St. Andrew – lego retaining wall, kerb, and drainage construction
  • Bruce Vale Bridge – bridge demolition completed; gabion works
  • Chance Hill, St. Lucy – drainage construction 
  • Cottage Vale, St. Philip – excavation
  • Eckstein Village, St. Michael –  milling and paving
  • Eden Lodge Main Road, St. Michael – milling and paving
  • Ellis Road, Bush Hall, St. Michael – milling and paving
  • Grant’s Gap, Westbury Road, St. Michael – milling and paving
  • Highway B2/Cherry Tree Hill, St. Andrew – (road closed) gabion repair
  • Highway D: Content to Dukes, St. Thomas– road reconstruction
  • Highway F Phase 1: St. John – drainage and retaining wall construction
  • Huntes Road, Carrington Village, St. Michael – milling and paving
  • King’s Street, St. Andrew – gabion and rip rap construction 
  • Layne’s Road, Brittons Hill, St. Michael – milling and paving
  • Laynes Bridge, St. Joseph – gabion construction
  • Link Road & Four Hill, St Peter – drainage construction
  • Marshall Road, Bush Hall, St. Michael – milling and paving
  • Mose Bottom, St. Andrew – retaining wall and drainage construction
  • Park Road – 1st, 2nd, 3rd Avenues, St. Michael – concrete works, milling & paving
  • Prior Park, St. James – road reconstruction (excavation)
  • Reece Road, St. Thomas – kerb and drainage construction
  • Rock Dundo, St. James to Gibbs, St. Peter – kerb construction
  • Sorrel Lane, Eden Lodge, St. Michael – milling and paving
  • St. Elizabeth’s Village, St. Joseph – gabion construction, road repairs
  • St. Margaret’s, St. John – excavation of BWA trenches
  • White Hill Phase 2, St. Andrew – gabion construction

Drain Cleaning

  • Ashdeane Village, Black Rock, St. Michael (in progress)
  • Bora Bora, Paynes Bay, St James
  • Cherry Tree Ave, Cleveland, Black Rock, St. Michael
  • Dayrells Road, St. Michael
  • James Street, Bridgetown  
  • Lower Burney, Mapp Hill, St. Michael
  • Riverland, St. Philip 
  • Rockley New Road, Christ Church
  • Ruby Park, St. Philip 
  • Sea Cliff Drive, St. Philip
  • Sealy Land, Bank Hall, St. Michael
  • St. Paul’s Ave, St. Michael 

Ongoing road works

St. Michael – St. Hill Road, off Belmont Road, is closed due to culvertrepairs. Motorists can divert through Quakers Road. The construction of slipper and kerb continues at Sargeants Village to channel the flow of water. The slipper and kerb has been poured and an additional section in the form of a curve will be excavated. Manhole repairs continue at the traffic lights adjoining Roebuck Street and Crumpton Street; excavation is finished, and masonry work continues. 90% of the footpath at Bridge Road has been excavated. The work will be completed shortly, and the formwork will start soon. Pothole patching is underway throughout the district.

Christ Church – Kerb construction and resurfacing are underway in Gibbons Terrace. Work to commence on a concrete protective barrier in Dayrells Hill. Drainage work will be done in Hilton Road, 3rd Avenue Dover and Ealing Park. Repairs will also be done to a grill on the footpath on Maxwell Main Road. Pothole patching is scheduled for Cane Vale New Road, Plumgrove, Kingsland, Chancery Lane, Silver Hill, Warners Main Road, Oistins Bus Terminal, Charnocks, Leadvale and Graeme Hall.

St. George – Masonry work will commence at Sweet Vale and Valley Main Road. Weeding will be done in Bailey Alley, Fairview, and Walkers. Mechanical debushing will be done in Groves and Ellerton. Drainage works will be done at Lower Estate Road. Patching is scheduled throughout the districts.

St. Lucy – Preparations are ongoing for a concrete footpath in Bourbon, and for repairs to the bridge and the headwall in Josey Hill. Pothole patching will be done at Northumberland and surrounding areas. Debushing will be done in Maycocks.

St. Peter – Repairing slipper and kerb and preparing for pothole patching in Maynards Retreat Road are scheduled. Work continues at Tom Bend Road. Farm Bridge remains closed until further notice; access to the Ronald Mapp Highway from Speightstown, and vice versa, is through Warleigh Road. 

St. James – Repairs are ongoing to manhole covers along Highway 1 in Road View and The Garden. Footpath repairs are scheduled for The Garden, and bollards will be installed in Oxnards.

St. Philip – Construction of a bounce-up as well as slipper and kerb continues in Atlantic Park. The reconstruction of the slipper and kerb is ongoing at Farm Road and Ruby Tenantry Road. Manhole reconstruction will be carried out at Industry Hall. Debushing will be carried out at Chapel, Cox Hill, and Union Development while manual weeding will be done at Ruby Development.

St. John – Masonry works will be done at Cliff Cottage and Small Town. Weeding will be carried out in Society and debushing in Church View, Small Town, and Bath Depot. Pothole patching will be carried out throughout the parish.

St. Thomas – Construction of a connecting footpath and retaining wall at Stoney Gully continues; concrete will be poured. Pothole patching and cleaning are scheduled for the Rock Hall Freedom route. Debushing, drainage work, and pothole patching are scheduled throughout districts.

St. Joseph/St. Andrew – Slipper and kerb will be constructed in Jackmans Alley, Orange Hill. Retaining wall and gabion construction as well as roadworks are ongoing at St. Elizabeth. Preparations for road paving are scheduled for Swanns. Pothole patching, drain cleaning and debushing are slated for both parishes. Persons are reminded not to drive on Swanns Bridge which has been closed due to deterioration.