Roadworks & drainage schedule for November 11-15, 2024

Road Marking 

The road marking crews of the Ministry of Transport and Works (MTW) will install reflective road studs (cat eyes) from the St. Thomas Parish Church roundabout heading northwards. Work will be done Monday to Thursday between 3:00 p.m. to 11:00 p.m., weather permitting.

Motorists are urged to avoid speeding through work areas while road markings are being done as this endangers the lives of workers and damages the freshly painted road markings.

Road Rehabilitation/ Road Construction

  • Animal Flower Cave Road, St. Lucy – paving
  • Babylon Road, St. Andrew – kerb construction
  • Bridgefield, St. Thomas – BWA works & design ongoing
  • Chance Hill, St. Lucy – box drain construction
  • Cherry Tree Hill, St. Andrew – preparations for road construction
  • Coggins Hill, St. Andrew – road closed due to excavation
  • Cottage Vale, St. Philip – excavation
  • Gibbons Terrace, Christ Church – box drain construction
  • Glenburnie, St. John – box drain & road base construction
  • Hangman’s Hill, St. Thomas – road preparation for use as a bypass road
  • Highway F, Bath, St. John – road base construction & building of box drain
  • Jemmotts Road, St. Lucy – kerb construction
  • Jericho to Middleton, St. George –  paving
  • King’s Street, St. Andrew – excavation & gabion installation
  • Laynes Bridge, St. Joseph – work on hold temporarily
  • Mellows, St. Joseph – extensive pothole patching
  • Millionaire Road, St. Peter – accommodation works
  • Prior Park, St. James – kerb removal, excavation, and setting out
  • Reece Road, St. Thomas – masonry work, suck well & box drain excavation
  • Rock Dundo, St. James to Gibbs, St. Peter – accommodation works
  • St. Simons, St. Andrew – reinforcement steel for box drain
  • Sweet Home Road, St. Peter – work on hold temporarily
  • Wakefield, St. John – paving
  • White Hill Phase 2, St. Andrew – road and drainage construction

Drainage Works

  • Barbarees Hill, St. Michael 
  • Bottom of Government Hill, St. Michael (in progress)
  • Halls Road, St. Michael (in progress)
  • Lower Collymore, St. Michael
  • Martindales Road, St. Michael 
  • Rihanna Drive, St. Michael
  • St. Barnabas Heights, St. Michael (in progress)
  • Trevor’s Way, Bridgetown 

Highway Beautification Programme (Debushing)

  • Babylon Road to Rock Hall (St. Peter) via Bawdens, St Andrew
  • Carlton Road from Highway 1 to Ronald Mapp Highway, St James
  • Harmony Hall, Station Hill, Waterford, Hothersal Turning, Lower Estate, St Michael
  • Highway 1C from Six Mens via Nesfield and Spring Hall to Bishops, St Lucy
  • Highway 3 Parris Hill to St Elizabeth, St Joseph
  • Highway 7 from Rendezvous Road to the Tom Adams Roundabout, Christ Church:              
  • Highway C from Lancaster via Endeavor to Hillaby, St Andrew
  • Highway M from Sterling to Parish Land, St Philip
  • Highway Q, Newton to Windsor, Christ Church:  
  • Lower and Upper Collymore Rock, St Michael
  • River Road, Highway 6, St Michael
  • Wildey Main Road, St. Michael

Ongoing road works

St. Michael – Phase 1 of the construction of a slipper and kerb and a new footpath at Long Gap are completed, and work has commenced on Phase 2. Manhole construction in King William Street, The City continues and work on the manholes at Lightfoot Lane will recommence shortly. Pothole patching is scheduled for districts.

St. John – Wakefield to be paved. Masonry works are ongoing at Malvern. De-bushing is scheduled for Clifton Hall, Sherbourne, and Hothersal.

St. Philip –  Construction of a bounce-up continues in Atlantic Park. In Ruby Tenantry and

Rock Hall, the construction of the slipper and kerb also continues. Weeding is scheduled for Fortesque. Pothole patching will be done in Rock Hall and throughout the parish.

St. George – Work continues on the short roads in Constant Tenantry and Daniel’s Land under the Community Access Road Transformation (CART) Project. Kerb work will be carried out in Rock Hall. Drainage work will be carried out in Walkers. Pothole patching is due for St. Judes, Ellesmere, Ellerton, and Glen Acres, Weeding and de-bushing are scheduled for Bridgecot South, Lower Newbury, Highway 3B, Greens No.2, Carmichael/Byde Mill.

Christ Church – Concrete works are scheduled for Gibbons Terrace, Enterprise, Sheraton Park, and Homestead Circle. Drainage work is being carried out at Pegwell and Dover. Pothole patching is scheduled for Gibbons and Gibbon Bog. Due to road depressions at Sayers Court, motorists, especially drivers of heavy-duty vehicles, are urged to be cautious while travelling around the small roundabout.

St. Joseph/St. Andrew – Extensive pothole patching is being carried out at Mellows while road repairs are to commence at Spa Hill. Persons are reminded not to drive on Swanns Bridge which has been closed due to deterioration. Installation of handrails is scheduled at Swanns. Gabion work is to commence in St. Elizabeth. The road at Trio Path is being reinstated and preparations are being made for paving. Manual and mechanical de-bushing continues from Lower Parks Road to Dark Hole and Fruitful Hill Cox Hill to Gaggs Hill, the junction of Turner’s Hall to Swanns to Rock Hall, Sailor Gully to Indian Ground to Welchtown, The Ridge to Springfield. Extensive pothole patching will take place from Cherry Tree Hill to Morgan Lewis Windmill.

St. Lucy – Work continues on Pie Corner Bridge; the road is closed until further notice. Motorists may divert at Well Road; local access will be granted. Work on Well Road No. 2 is soon to be completed under the C.A.R.T Programme. Pot-hole patching will be done throughout districts.

St. Peter – Debushing at Mount Brevitor via French Village to Indian Ground. Pothole patching is being done throughout the parish. Farm Bridge remains closed until further notice; access to the Ronald Mapp Highway from Speightstown, and vice versa, is through Warleigh Road. 

St. James – Pothole patching is scheduled for Highway 1. Manhole covers are being repaired along Highway 1 in  Porters and Holetown. Drainage work is scheduled for Hoytes Village. Headwall construction has commenced in Durants. Pothole patching is scheduled throughout the districts.

St. Thomas – Preparations are being made for paving in Stoney Gully. Extensive pothole patching is being carried out in Airy Cot, Dunscombe, and Canefield.

MTW advises pedestrians and motorists to obey traffic wardens, pay attention to signage, and exercise due care and attention when traversing work sites.

Friday, November 8, 2024