ROAD WORKS ACTIVITIES FOR NOVEMBER 25-29, 2024

Footpath construction in Belleplaine, St Andrew by the team from the Haggatts Depot.

Road Rehabilitation/ Road Construction

  • Babylon Road, St. Andrew – box drains and kerb & slipper construction
  • Bottom Bay,  St. Philip – paving
  • Bridgefield, St. Thomas – BWA works & design ongoing
  • Chance Hill, St. Lucy – box drain construction
  • Cherry Tree Hill, St. Andrew – preparations for road construction
  • Coggins Hill, St. Andrew – restricted access
  • Cottage Vale, St. Philip – cadastral surveys ongoing
  • Glenburnie, St. John – box drain & road base construction
  • Hangman’s Hill, St. Thomas – road preparation for use as a bypass road
  • Highway F, Bath, St. John – road base construction; road closed
  • Jemmotts Road, St. Lucy – BWA works ongoing
  • Jericho to Middleton, St. George – milling
  • King’s Street, St. Andrew –gabion works
  • Laynes Bridge, St. Joseph – gabion works and culvert construction
  • Lodge Hill, St. Michael – paving
  • Prior Park, St. James – wells and kerb construction; single lane traffic
  • Reece Road, St. Thomas – masonry work, suck well & box drain excavation
  • Rock Dundo, St. James to Gibbs, St. Peter –kerb construction
  • St. Simons, St. Andrew – box drain continue
  • Sweet Home Road, St. Peter –on hold temporarily
  • White Hill Phase 2, St. Andrew – road and drainage construction

Drainage Cleaning

  • Berlin Road, Woodbourne, St. Philip
  • Burbon, St. Lucy
  • #37 Chancery Lane, Christ Church.
  • Dayrells Road, Christ Church
  • T junction at Collenton, St. Lucy
  • Husband’s Main Road, St. Lucy
  • Jackson Tenantry Road, St. Michael
  • Reece Road #2, Brittons Hill, St. Michael
  • Ruby Main Road, St. Philip
  • 2nd Ave Sion Hill, St. James 
  • #19 South Point, Atlantic Shores, Christ Church
  • South View Drive, Cane Garden Park, St. Thomas .
  • Trevor’s Way/ Bridgetown Port (continuing)

Highway Beautification Programme (Debushing)

  • St Lucy:          Highway B3 from Junction with Highway 1C to Date Tree Hill
  • St. Andrew:     Highway B from Junction with Ermie Bourne Highway to Canefield Road
  • St Thomas:      Highway D, Dunscombe to Cane Garden
  • St. Joseph:       Highway 3A from Sugar Hill to Bruce Vale
  • St. Philip:        Highway N Oldbury to Long Bay via Rices, Crane, and Belair
  • St George:       Highway 4 from Salters to Drax Hall, Salters Road and Highway X to Cottage, Highway 5 Salters to Six Roads
  • St. Michael:     Fairfield Main Road, Deacons Road and Exmouth Gap, Bank Hall Cross Road, Bridge Road, Welches Road, Pine Road, Culloden Road, Dalkeith Road and Garrison Road
  • St James/ St.Michael: Husbands Main Road, Thorpes Main Road and Holders Main Road

Ongoing road works

St. Michael – Compromised footpaths are being repaired along Pine East-West Boulevard Work on the footpaths and slipper and kerb in Long Gap have been completed. Work is on hold at King William Street and at Lightfoot Lane in The City. Pothole patching is scheduled for districts.

St. John – Wakefield Road has been paved. Masonry works are ongoing at Malvern. Mechanical de-bushing is scheduled from Stuart Hill to Palmers.

St. Philip –  Construction of a bounce-up continues in Atlantic Park. In Ruby Tenantry, the construction of the slipper and kerb also continues. Ruby Plantation Road will be graded and marl filled. De-bushing is scheduled for Rices and Kirtons while weeding is scheduled for Fortesque. Pothole patching will be done in Rock Hall and throughout the parish.

St. George – Work continues on the short roads in Constant Tenantry and Daniel’s Land under the Community Access Road Transformation (CART) Project. Kerb construction is ongoing in Rock Hall. Drainage work will be carried out on Ellerton Main Road. Pothole patching is due for Cottage Tenet, Middleton and Flat Rock. Weeding and de-bushing are scheduled for Walkers, Highway 3B, Market Hill, Bridgecot South, Lower Newbury and Workmans.

Christ Church – Work on the footpaths will recommence in Hastings. Concrete works are scheduled for Gibbons Terrace, Inch Marlow, and Sheraton Park. Drainage work is being carried out at Fairholme Gardens and Inch Marlow. Pothole patching is scheduled throughout the district. Debushing is scheduled for St. Davids/Bannatyne, Gibbons Boggs, and Lower Carters Gap. Due to road depressions at Sayers Court, motorists, especially drivers of heavy-duty vehicles, are urged to be cautious while travelling around the small roundabout.

St. Joseph/St. Andrew – Road repairs continue at Spa Hill. Persons are reminded not to drive on Swanns Bridge which has been closed due to deterioration. Handrails are to be completed at Swanns. Gabion work at St. Elizabeth continues. Road works at Trio Path and Upper Parks. Manual and mechanical de-bushing continue on Ermie Bourne Highway, Cox Hill to Gaggs Hill, Lower Walkers to Bawdens and Greenalnd to Farley Hill. Pothole patching will take place from Cherry Tree Hill to Morgan Lewis Windmill.

St. Lucy – Work continues on Pie Corner Bridge; the road is closed until further notice. Motorists may divert at Well Road; local access will be granted. Work on Well Road No. 2 is soon to be completed under the C.A.R.T Programme. Debushing will be carried out from Hope Road to River Bay. Pot-hole patching will be done throughout districts.

St. Peter – Debushing at Pleasant Hall to Alleynedale to Rose Hill, Lonesome Hill to Indian Ground to Welchtown. Pothole patching is being done throughout the parish. Farm Bridge remains closed until further notice; access to the Ronald Mapp Highway from Speightstown, and vice versa, is through Warleigh Road. 

St. James – Pothole patching being carried out on Highway 1. Manhole covers are being repaired along Highway 1 in  Porters and Holetown. Drainage work is ongoing at Hoytes Village. A headwall is being constructed in Durants. Pothole patching is scheduled throughout the districts.

St. Thomas – Preparations are being made for paving in Stoney Gully. Debushing in Edgehill, Shop Hill and Cane Garden Development. Pothole patching scheduled throughout districts.

MTW advises pedestrians and motorists to obey traffic wardens, pay attention to signage, and exercise due care and attention when traversing work sites.