2ND PHASE OF WILDEY TRIANGLE PAVED UNDER HIGHWAY MAINTENANCE PROGRAMME

Phase 2 of the rehabilitation of the Wildey Triangle, located along the ABC Highway in St. Michael, has been completely paved. Executed under the Ministry of Transport and Works’ (MTW) Highway Maintenance Programme, in collaboration with contractor C.O. Williams Construction Ltd., this phase experienced periodic closures due to a few delays. These delays were primarily […]
Road Works Activities For June 16 – 20, 2025

Road Marking The Road Marking crew of the Ministry of Transport and Works (MTW) will complete the remarking of the newly paved section of the D’Arcy Scott Roundabout to the Welches Roundabout, following a delay. Reflective studs (cat eyes) will also be installed. The northbound and southbound lanes from the bottom of BET Hill to […]
Repairs to Culvert in Farm Tenantry Road, St. Peter

A crew from the Jerusalem Depot of the Ministry of Transport and Works (MTW) will repair a culvert on a section of Farm Tenantry Road from the junction of KNR Husbands Highway and Farm Tenantry Road to the Y-junction of Farm Tenantry Road in St. Peter. As a result, the road will be closed temporarily […]
Cleaning of Median and Slipper on Mighty Grynner Highway, St. Michael

A crew from the Richmond Depot of the Ministry of Transport and Works (MTW) will clean the median and slipper along the Mighty Grynner Highway, St. Michael, from Tuesday, June 10, to Friday, June 13, 2025, weather permitting. To ensure the safety of the MTW staff and the travelling public, the northbound lane will be […]
Infra Milling and Paving 1st and 2nd Avenue Rouen Road, Off of Rouen Road, My Lords Hill St. Michael

From Thursday, June 5, 2025, the Ministry of Transport and Works (MTW), will mill and pave 1st and 2nd Avenue Rouen Road, just off Rouen Road, My Lords Hill, St. Michael. Infra Construction Inc. will carry out the work under the MTW’s Focused Road Works programme, which is expected to take approximately two weeks. Work […]
UPDATE ON REECE ROAD ST. THOMAS – WORK SOON COMPLETED

Paving has been completed on Reece Road in St. Thomas, however, drainage work is still being undertaken. The Ministry of Transport and Works (MTW) began work on Reece Road, St. Thomas in April 2024 under the Scotland District Road Rehabilitation Programme, in conjunction with the contractor The China National Complete Plant Import and Export Corporation […]
Guard rails continue to be installed on bridges along Highway 2A

New guard rails will be installed along three additional bridges on Highway 2A, as the Ministry of Transport and Works (MTW) continues to improve bridge safety across the island. Coles Engineering, on behalf of MTW, will install and renovate guard rails on The Whim Bridge, St. Peter on Thursday, May 22, from 10:00 a.m. to […]
GUARD RAILS TO BE INSTALLED ON TWO BRIDGES ALONG HIGHWAY 2A

New guard rails will be installed along two bridges on Highway 2A, St. Peter, as the Ministry of Transport and Works (MTW) seeks to improve bridge safety across the island. Coles Engineering, on behalf of MTW, will install guard rails on the Mile and Quarter Bridge on Thursday, May 15, and Friday, May 16, between […]
TEMPORARY CLOSURE OF NORTHBOUND SECTION OF WILDEY TRIANGLE

The Ministry of Transport and Works (MTW) advises the public that the northbound section of the Wildey Triangle in St. Michael, from Carters General Store to the back of Courtesy Garage, has been temporarily closed until further notice. This section of the road, which is currently under repair, has become severely waterlogged due to recent […]
ROAD WORKS ACTIVITIES FOR May 12 – 16, 2025

Road Marking The Road Marking crew of the Ministry of Transport and Works (MTW) will remark the newly paved section of highway from the D’Arcy Scott Roundabout to the Welches Roundabout. 90% of the section of highway from Deighton Griffith Secondary School to the Edwy Talma Roundabout has been remarked, only the edge lines are […]