Road Marking
The Road Marking crew of the Ministry of Transport and Works (MTW) will paint school pedestrian crossings on Highway 7. They will also repaint road markings from the Deighton Griffith Secondary School to the Edwy Talma Roundabout, as well as from Top Rock to the Errol Barrow (Graeme Hall) Roundabout. Work will be done Monday to Thursday between 6:00 p.m. and 4:00 a.m., weather permitting.
Motorists are urged to avoid speeding through work areas while road markings are being done as this endangers the lives of workers and damages the freshly painted road markings.
Road Rehabilitation/ Road Construction
- Airy Hill, St. Joseph – culvert construction
- Babylon Road, St. Andrew – drainage & roadbase construction
- Bruce Vale Bridge – bridge demolition completed; surveying & gabion works
- Chance Hill, St. Lucy – kerb and culvert construction
- Coggins Hill, St. Andrew – stub wall, culvert & drainage construction
- Cottage Vale, St. Philip – roller compacted concrete (RCC)
- D’Arcy Scott Roundabout to Welches Roundabout, St. Michael – milling & paving
- Eckstein Village, St. Michael – accommodation works
- Glenburine Road, St. John – gabion construction
- Grant’s Gap, Westbury Road, St. Michael – milling & paving
- Highway B2/Cherry Tree Hill, St. Andrew – drainage & gabion construction
- Highway D: Content to Dukes, St. Thomas – road reconstruction
- Hangman Hill to Bridgefield, St. Thomas – road reconstruction; section closed
- Highway F Phase 1, St. John – paving & road construction
- Huntes Road, Carrington Village, St. Michael – milling & paving
- King’s Street, St. Andrew – gabion foundation backfilling
- Laynes Bridge, St. Joseph – culvert construction
- Link Road/Four Hill, St. Peter – suckwell construction
- Mose Bottom, St. Andrew – drainage construction
- Park Road – 1st, 2nd, 3rd Avenues, St. Michael – concrete works, milling & paving
- Prior Park, St. James – road reconstruction
- Reece Road, St. Thomas – drainage construction
- St. Margaret’s, St. John – kerb and culvert construction
- Sunflower Drive, Cane Garden, St. Michael – milling & paving
- White Hill Phase 2, St. Andrew – gabion construction
- Wildey Triange, St. Michael – road rehabilitation/milling & paving
- Yearwood Road, St. Joseph – milling & paving
Drain Cleaning
- 5th Aveuve Holders Land, Brandons, St. Michael
- Adam’s section of the ABC Highway
- Durants Corner, Christ Church
- Elizabeth Park, Christ Church
- James Street, Bridgetown
- Paynes Bay, St.James
- Todds Corner to Melvin Hill, St. Joseph

Ongoing road works
St. Michael – The construction of the slipper and kerb at Sargeants Village is completed. Excavation is due to start to facilitate building an addition 20 feet. Repairs to the slipper and kerb at Tweedside Road are 90% completed; precasted concrete slabs are being worked on in the meantime. Manhole repairs and replacement will start on the Mighty Gryner Highway. Two manholes on Constitution Road have been cast; work continues on the manhole at Crumpton Street. Reconstruction of the footpath at Bridge Road is in the final stage and now requires clean-up work. Concrete works to a manhole at the Waterford roundabout near the Combermere School are finished. Pothole patching is scheduled throughout the parish.
Christ Church – Repairs are ongoing to a drain on a footpath on Maxwell Main Road. Kerb construction and road reinstatement are underway in Gibbons Terrace. Drainage work will be done in Harmoney Hall, St. Lawrence Gap. Debushing is scheduled for Wilcox Hill. Pothole patching is scheduled for Atlantic Shotes, Elizabeth Park, Graeme Hall, Inch Marlow, Kingsland, Leadvale, Long Beach, Plumgrove, Silver Hill, St. David’s, and Warners.
St. George – Preparation for road surfacing will be carried out on Valley Main Road; Weeding will be done in Rowans Park, while debushing will be done in Drax Hall Hope. Drainage work will continue in Price Road.
St. Lucy – Masonary work is scheduled for Josey Hill Bridge. Drain cleaning will be done along Charles Duncan O’Neal Highway. Pothole patching is scheduled for Mount Gay, Lamberts and Harrison’s.
St. Peter – Repairs continue to the slipper and kerb on Maynards Retreat Road. Masonary work is scheduled for the junction of Tom Bend Road and Ashton Hall Main Road. Debushing will be done in Maynards Development. Farm Bridge remains closed until further notice; access to the Ronald Mapp Highway from Speightstown, and vice versa, is through Warleigh Road.
St. James – Repairs are ongoing to manhole covers continue along Highway 1 between Porters and Lower Carlton, while cleaning of road stuff will be done from Dairy Meadows and Holder’s Hill.
St. John – Masonry works continue in Small Town. Weeding will be carried out on Society Hill and debushing in Palmer, Wakefield and Supers. Pothole patching will be carried out throughout the parish.
St. Philip – Construction of a haunch and slipper continues in Atlantic Park. The reconstruction of slipper and kerb continues in Farm Road and Ruby Tenartry. Manual weeding will be done in Ruby Development and Duncans while mechanical debushing will be done in Chapel.
St. Thomas – Plastering of the retaining wall at Stoney Gully continues. Debushing, drainage work, and pothole patching are scheduled throughout districts.
St. Joseph/St. Andrew – The construction of a box drain and walk over is scheduled for Bathsheba Park. Road construction is ongoing at Swanns, while slipper and kerb continues to be built at Jackmans Alley, Orange Hill. Debushing, patching and drainage work are scheduled for throughout the parishes. Persons are reminded not to drive on Swanns Bridge which has been closed due to deterioration.