Road Works Activities For June 16 – 20, 2025

Road Marking 

The Road Marking crew of the Ministry of Transport and Works (MTW) will complete the remarking of the newly paved section of the D’Arcy Scott Roundabout to the Welches Roundabout, following a delay. Reflective studs (cat eyes) will also be installed. The northbound and southbound lanes from the bottom of BET Hill to the turnoff near Pine East/West Boulevard, St. Michael, will also be remarked. The roundabout at Coverley will be repainted. Work will be done from Monday to Thursday, between 6:00 p.m. and 4:00 a.m., weather permitting

Motorists are urged to avoid speeding through work areas while road markings are being done as this endangers the lives of workers and damages the freshly painted road markings.

Road Rehabilitation/ Road Construction

  • Airy Hill, St. Joseph – culvert construction
  • Babylon Road, St. Andrew – drainage & road construction
  • Bruce Vale Bridge – bridge demolition done; surveying & gabion works ongoing
  • Coggins Hill, St. Andrew – stub wall, culvert & drainage construction
  • Cottage Vale, St. Philip – roller compacted concrete (RCC)
  • Dacosta Drive, Eden Lodge, St. Michael – road reconstruction
  • Eagle Hall Road, St. Michael – road rehabilitation
  • Eden Lodge (Main Avenue), St. Michael – road rehabilitation
  • Glenburine Road, St. John – gabion construction
  • 3rd Ave, Goodland, St. Michael – road rehabilitation
  • Highway B2/Cherry Tree Hill, St. Andrew – drainage & gabion construction
  • Highway 1C/Hope Road, St. Lucy – road reconstruction
  • Highway D Content to Dukes, St. Thomas – road reconstruction
  • Hangman Hill to Bridgefield, St. Thomas – road reconstruction; section closed
  • Highway F Phase 1, St. John – paving & road construction
  • Huntes Road, Carrington Village, St. Michael – kerb construction, mill & pave
  • King’s Street, St. Andrew – gabion foundation backfilling 
  • Laynes Bridge, St. Joseph – culvert construction
  • Lodge Road, St. Michael – road rehabilitation: excavation, deep milling, paving
  • Mose Bottom, St. Andrew – drainage construction
  • Prior Park, St. James – road reconstruction
  • Sorrel Lane, St. Michael – road rehabilitation
  • St. Margaret’s, St. John – kerb and culvert construction
  • White Hill Phase 2, St. Andrew – accommodation works

Drain Cleaning

  • 5th Ave Holders Land, Brandons, St. Michael
  • Advent Avenue, Bank Hall, St. Michael
  • Allen Street, Spry Street, St. Michael 
  • Barbarees Hill, St. Michael
  • Barracks Road, Station Hill, St. Michael
  • Brathwaite’s Gap, Dayrells Road, St. Michael
  • East Coast Road, St. Andrew (in progress)
  • Fernihurst to Bridge Gap, St. Michael (in progress)
  • Glebe, St. George (in progress)
  • Glydor Gardens, Clermont, St. James 
  • Grazettes, St. Michael
  • Greenfield, Bridgetown
  • Hibiscus Ave, Sunset Crest, St. James
  • Hoytes Village, St. James 
  • Oistins, Ch. Ch. (In progress)
  • Pinders Ave, Culloden Road, St. Michael
  • Rock Dundo, St. James 
  • Skeetes Road, Jackmans, St. Michael
  • Taitt Hill, St. George (in progress)
  • Tuscany Gardens, Oldbury, St. Philip
  • Yorkshire Development, Christ Church

Ongoing road works

St. Michael – Cleaning of the medium and slipper on the Mighty Grynner Highway continues. As a result, the northbound lane will be closed from 9:30 a.m. to 1:00 p.m. Manhole repairs and excavation also continue on the Mighty Grynner Highway. Repairs to a head wall in Martindales Road outside The St. Michael School continue. Slipper and kerb repair in Clapham is presently on hold. The manhole on River Road has been completed. Pothole patching is scheduled throughout the parish.

St. George – Weeding continues in Rowans Park. Debushing is scheduled at Buttals, while drainage work is scheduled for Charles Rowe Bridge. Pothole patching will be done at Bulkley, Brighton, Frenches, Middleton, and Ellerton, pending weather.

Christ Church –  In Parish Land, repairs are ongoing to a retaining kerb wall. Drainage and clean-up works continue in Oistins (Near Grannies Restaurant and the Bus Terminal), while debushing is planned for Graeme Hall Roundabout and Newton/entrance to Lower Greys. Pothole patching is scheduled for Graeme Hall, Warners Main Road, Briar Hall, Long Beach, Gibbons Main Road, Chancery Lane, Silver Hill, Elizabeth Park, Hopewell Main Road, and Breedy Land.

St. Philip – Excavating, compacting, road widening, and slipper and kerb construction continue in Johnson Development. Repairs to footpaths in Four Square Valley are ongoing. Manual weeding is being carried out in Ruby Development, while mechanical debushing will be done on Ruby Main Road and Padmore Village. Pothole patching to be done throughout the districts.

St. Lucy – Debushing is scheduled for Alexandria, and drain cleaning will be carried out in Benthams. Pothole patching is scheduled for Pie Corner, Cave Hill, and Maycocks Terrace.

St. Peter – Repairs will be carried out to a culvert at the junction of KNR Husbands Highway and Farm Tenantry Road. Repairs continue to the box drain, slipper, and kerb on Maynards Retreat Road. Pothole patching is scheduled for Mount Brevitor to French Village, and Warleigh Road.  Farm Bridge remains closed until further notice. Access to the Ronald Mapp Highway from Speightstown, and vice versa, is through Warleigh Road. 

St. James – Repairs to manholes and footpaths continue along Porters Road. Pothole patching will be done in Prospect, Holders Hill, West Terrace, and Mullins Road.

St. John – Masonry works continue in St. John Parish Church. Weeding will be carried out in Colleton, and debushing will be done at Gall Hill, Small Town, and from Guinea to Kendal. Pothole patching will be carried out in New Castle, Martin Bay, St Margaret’s, Foster Hall, and Guinea.

St. Thomas – Construction of the spirolite pipe culvert is planned for Mount Wilton. Footpath and retaining wall completed at Stoney Gully, clean up of work site ongoing. Debushing, drainage work, and pothole patching are scheduled throughout the districts.

St. Joseph/St. Andrew –  Construction of the concrete drain at Tent Bay and slipper and kerb in Lakes Village continues. Road construction is ongoing at Swanns. The construction of a box drain for Bathsheba Park is almost completed. Repairs are ongoing to the manholes in the footpaths at Belleplaine. In Springfield, the construction of a spirolite pipe culvert will commence. Debushing, patching, and drainage work are scheduled throughout the parishes. Persons are reminded not to drive on Swanns Bridge, which has been closed due to deterioration.