Road Marking
The Road Marking crew of the Ministry of Transport and Works (MTW) will remark the newly paved section of highway from the D’Arcy Scott Roundabout to the Welches Roundabout. 90% of the section of highway from Deighton Griffith Secondary School to the Edwy Talma Roundabout has been remarked, only the edge lines are left to be completed. Work will be done on Monday to Thursday, between 6:00 p.m. and 4:00 a.m., weather permitting.
Motorists are urged to avoid speeding through work areas while road markings are being done as this endangers the lives of workers and damages the freshly painted road markings.
Road Rehabilitation/ Road Construction
- Airy Hill, St. Joseph – culvert construction
- Babylon Road, St. Andrew – drainage & roadbase construction
- Bruce Vale Bridge – bridge demolition completed; surveying & gabion works
- Chance Hill, St. Lucy – kerb and culvert construction
- Coggins Hill, St. Andrew – stub wall, culvert & drainage construction
- Cottage Vale, St. Philip – roller compacted concrete (RCC)
- Dougling Road, Weston, St. James – milling and paving
- Eckstein Village, St. Michael – accommodation works
- Glenburine Road, St. John – gabion construction
- Grant’s Gap, Westbury Road, St. Michael – milling & paving
- Highway B2/Cherry Tree Hill, St. Andrew – drainage & gabion construction
- Highway D: Content to Dukes, St. Thomas – road reconstruction
- Hangman Hill to Bridgefield, St. Thomas – road reconstruction; section closed
- Highway F Phase 1, St. John – paving & road construction
- Huntes Road, Carrington Village, St. Michael – milling & paving
- King’s Street, St. Andrew – gabion foundation backfilling
- Laynes Bridge, St. Joseph – culvert construction
- Link Road/Four Hill, St. Peter – suckwell construction
- Mose Bottom, St. Andrew – drainage construction
- Park Road – 1st, 2nd, 3rd Avenues, St. Michael – concrete works, milling & paving
- Prior Park, St. James – road reconstruction
- Reece Road, St. Thomas – drainage construction
- St. Margaret’s, St. John – kerb and culvert construction
- White Hill Phase 2, St. Andrew – gabion construction
- Wildey Triangle, St. Michael – road rehabilitation/milling & paving
- Yearwood Road, St. Joseph – milling & paving
Drain Cleaning
- ABC Highway going East
- Belmont Road, St. Michael
- Black Rock, St. Michael
- Canal running from Blades & Williams
- 2nd Ave Cane Garden, St. Thomas
- Date Tree Hill, St. Peter
- Elizabeth Park, Christ Church
- Greenfields, Bridgetown
- 5th Ave Holders Hill, St. Michael
- James Street, Bridgetown
- Lakes Folly, Bridgetown
- Mount Standfast, St. James
- Orange Cottage, St. Joseph
- Paynes Bay, St.James
- 1st Ave Promenade Road, Bush Hall, St. Michael
- Taitt Hill, St. George (in progress)
- Tudor Street, Bridgetown
- Wellington Street, Bridgetown

Ongoing road works
St. Michael –Manhole repairs and excavation continue on the Mighty Grynner Highway. Work continues on the manholes at Crumpton Street and at Constitution Road, in the bus lay by. Two other manholes at Constitution Road have been cast in concrete and are currently curing. Repairs have commenced on a manhole on River Road. Concrete works to the footpathon Collymore Rock Main Road have been completed, the curing process is in progress. Concrete works at Sargeants Village have also been completed, the area is being tidied. Pothole patching is scheduled throughout the parish.
Christ Church – Masonry work continues at the Southern Plaza/Massy entrance. Work continues in Gibbons Bogg where road edge reinstatement is ongoing. Reinstatement and drain construction also continue in Gibbons Terrace. Drainage work continues in Welches, where manholes are beong cleaned. Debushing will be done in Hopewell and Ealing Park. Pothole patching is scheduled for Wilcox, Long Beach, St. David’s, Homestead, Ealing Park, Callenders, Atlantic Shores, Elizabeth Park, Plumgrove, Lisbonville and Leadvale.
St. George – Road surfacing on Valley Main Road has been completed. Weeding continues in Rowans Park, while debushing is being done in Eastlyn and Carmichael. Drainage work is to be done in Exchange.
St. Lucy – Masonary work is scheduled for Mount View. Drain cleaning continues along Charles Duncan O’Neal Highway (Checker Hall and Bourbon). Debushing is also being carried out along the Charles Duncan O’Neal Highway. Pothole patching is scheduled for Friendly Hall, Maycocks, Mount Gay and Chance Hall Road.
St. Peter – Repairs continue to the slipper and kerb on Maynards Retreat Road. Farm Bridge remains closed until further notice; access to the Ronald Mapp Highway from Speightstown, and vice versa, is through Warleigh Road.
St. James – Repairs to manhole covers continue along Highway 1 – Fitts Village to Road View while bollards will be installed at Oxnards Main Road.
St. John – Masonry works continue in Cliff Cottage and St. John Parish Church. Weeding will be carried out in Colleton and debushing at the Bath Depot, Bath Hill and Hothersal. Pothole patching will be carried out throughout the St John districts – Woodland to Guinea and Guinea to Massiah Street.
St. Philip – In Johnson Development – excavating, compacting, road widening and slipper and kerb construction continue. Repairs to footpaths in Four Square Valley also continue. Manual weeding is being carried out in Ruby Development, while manual debushing continues on Ruby Main Road. Pothole patching to be done throughout the district.
St. Thomas – Plastering of the retaining wall at Stoney Gully continues. Debushing, drainage work, and pothole patching are scheduled throughout districts.
St. Joseph/St. Andrew – Construction of slipper and curb at Lakes Village. The construction of a box drain and walk over continues for Bathsheba Park. Road construction is ongoing at Swanns, while slipper and kerb continue to be built at Jackmans Alley, Orange Hill. Repairs will be done to the footpaths in Belleplaine. Debushing, patching and drainage work are scheduled throughout the parishes. Persons are reminded not to drive on Swanns Bridge which has been closed due to deterioration.