ROAD WORKS ACTIVITIES FOR SEPTEMBER 15 – 19, 2025

Road Marking

The Road Marking crew of the Ministry of Transport and Works (MTW) will continue remarking pedestrian crossings for the new school year in Christ Church, St. Michael, St. George and St. James this week. Work will be done Monday to Thursday, between 6:00 p.m. and 4:00 a.m., weather permitting.   

Motorists are urged to avoid speeding through work areas while road markings are being done, as this endangers the lives of workers and damages the freshly painted road markings.

Road Rehabilitation/ Road Construction

  • 1st and 2nd Ave, Rouen Road, My Lords Hill, St Michael – road rehabilitation
  • 3rd Ave, Goodland, St. Michael – road rehabilitation
  • Airy Hill, St. Joseph – culvert construction
  • Babylon Road, St. Andrew – drainage & road construction
  • Bruce Vale Bridge – constructing the bridge foundation
  • Coggins Hill, St. Andrew – final 380m to be paved
  • Cottage Vale, St. Philip – roller compacted concrete (RCC)
  • Dacosta Drive, Eden Lodge, St. Michael – road rehabilitation
  • Glenburnie Road, St. John – gabion construction
  • Hangman Hill to Bridgefield, St. Thomas – road reconstruction; section closed
  • Highway 1C/Hope Road, St. Lucy – road reconstruction
  • Highway B2, St. Andrew – drainage & gabion construction
  • Highway C, St. James – road rehabilitation
  • Highway D, Content to Dukes, St. Thomas – road reconstruction
  • Highway F Phase 1, St. John – paving & road construction
  • King’s Street, St. Andrew – paving 
  • Laynes Bridge, St. Joseph – culvert construction
  • Lodge Hill, St. Michael – road rehabilitation
  • Mose Bottom, St. Andrew – road and drainage construction
  • Mount Brevitor, St. Peter – road rehabilitation (sidewalks and slipper, and kerb)
  • Prior Park, St. James – road reconstruction
  • Sorrel Lane, Eden Lodge, St. Michael – road rehabilitation
  • St. Margaret’s, St. John – kerb and culvert construction
  • Warrens Terrace, St. Michael – milling and paving
  • White Hill Phase 2, St. Andrew – accommodation works

Drain Cleaning

  • Lr. Beckles Road, St. Michael 
  • Chelsea Road, St. Michael
  • Haggatt Hall, St. Michael (in progress)
  • Harmony Hall, St. Michael (in progress)
  • Highland, St. Thomas
  • Holetown, St. James (in progress)
  • Maxwell Road, Christ Church
  • Salters Tenantry Road, St. George
  • Spencer’s, Christ Church
  • Stanmore, Black Rock, St. Michael 
  • St. Martin’s, St. Philip
  • Tamarind Avenue, Country Road, St. Michael

Ongoing road works

St. Michael – Repairs  are being done to a footpath in Parkinson Field, The Pine,

where bollards are being placed to prevent vehicles from mounting the footpath. Repairs to a culvert in Whitepark Road has commenced. In Grazettes, in the vicinity of the primary school, concrete bollards are being installed. Repairs to a damaged footpath has commenced in Roebuck Street. On the Mighty Grynner Highway, just outside of Central Purchasing, repairs to a section of the road which has sunken has commenced. Excavation work has been done and the area has now to be cleared of debris for inspection by an engineer. The construction of the slipper and kerb in Clapham is on hold.

Christ Church –  Repairs to a damaged footpath in Hastings are being carried out where concrete slabs are being precasted then placed in position. Construction of the footpath in Dayrells Hill (Lower Greys) continues. Drainage and debushing are planned for Searles Roundabout and Wilcox Hill. Pothole patching is scheduled for Seawell, Gall Hill, Silver Hill, Plumgrove, Maxwell Plains, Montrose, Kendal Hill Park, Elizabeth Park and  Kingsland.

St. George – Weeding is scheduled in Roach Village, while debushing is planned at Boarded Hall. Drainage work will be carried out in Lower Estate. Masonry work, which includes kerb construction and accommodation, is scheduled for Superlative. Pothole patching will be done in Old Works Hill and from Love Rock Corner towards Eastlynne Hill.

St. Philip – Manhole repairs are being carried out in Halton Main Road, while slipper and kerb reconstruction are ongoing in Johnson Development. Slipper reconstruction is ongoing in Foursquare Valley. Slipper and kerb cleaning is scheduled around Six Roads Hub. Weeding will be done in Ruby Development, while mechanical debushing will be done in Fortesque. Bus stop and sign replacement will be carried out in districts. Pothole patching is scheduled throughout the parish.

St. Lucy – Concrete works are being done in Sutherland No.2 and Josey Hill. Drain and well cleaning will be carried out in Date Tree Hill, Sutherland No. 1 and Rock Hall Road. Debushing will be done  out in Cluff and Jordans. Pothole patching is scheduled for Stroude Bay, Grape Hall, Salmonds and Cove Bay Road.

St. Peter – Work continues on the box drain and slipper and kerb along Maynard’s Retreat Road. Weeding is being done in Mango Lane and Queens Street while debushing is being carried out in Ashton Hall, Tom Bend Road and Alleynedale. Drainage work continues in Sunset Heights. Pothole patching is scheduled for Farm Road, Battleys, Indian Ground and The Rock. Farm Bridge remains closed until further notice. Access to the Ronald Mapp Highway from Speightstown, and vice versa, is through Warleigh Road.   

St. Thomas –The footpath and retaining wall at Stoney Gully are done, and preparation for paving has started. Pothole patching, drain cleaning and debushing throughout the district.

St. James –Repairs are ongoing on two box drains in Porters Road. Excavation works are planned for slipper and kerb construction near the Archives Department and masonry work in The Whim. Drain cleaning on Highway 1, from Vauxhall Road to Road View. Pothole patching is scheduled for Upper & lower Mount Standfast, Porters Road, Clarkes Road, Paynes Bay, Durants Village, Warrens Park North, Husbands Heights, Wanstead Heights, Bagatelle Terrace and Prior Park Terrace. 

St. John – Masonry works are continuing in Consett and Coach Hill. Weeding will be carried out in Bath Land while debushing will be done in Palmers, Sargeant Street and Bath Depot Pothole patching is scheduled for Pothouse, Bath Land, Colleton Garden and Colleton.

St. Joseph/St. Andrew – Following the closure of Melvin Hill Bridge, Springfield to Newton Crescent is being debushed, trees are being trimmed and resurfacing is also being done to facilitate the use of this road as a bypass road. The construction of a spirolyte pipe culvert has also been done. Motorists and public transportation can use this route during the closure of the bridge. Bridge poles are being erected in Lakes and Haggatts. Mechanical debushing and cleaning of outfall drains are also taking place in Bawdens. Construction of the slipper and kerb in Lakes Village continues. Road construction is ongoing at Swanns. Debushing, patching, extensive pothole patching, and drainage work are scheduled throughout the parishes. Persons are reminded not to drive on Swanns Bridge, which has been closed due to deterioration.

Share the Post: