Road Rehabilitation/ Road Construction
- 1st and 2nd Ave, Rouen Road, My Lords Hill, St Michael – road rehabilitation
- 3rd Ave, Goodland, St. Michael – road rehabilitation
- Airy Hill, St. Joseph – culvert construction
- Babylon Road, St. Andrew – drainage & road construction
- Bruce Vale Bridge – constructing the bridge foundation
- Coggins Hill, St. Andrew – stub wall, culvert & drainage construction
- Cottage Vale, St. Philip – roller compacted concrete (RCC)
- Dacosta Drive, Eden Lodge, St. Michael – road rehabilitation
- Eagle Hall Road, St. Michael – road rehabilitation
- Eden Lodge (Main Avenue), St. Michael – road rehabilitation
- Foul Bay, St. Philip – milling and paving
- Glenburine Road, St. John – gabion construction
- Hangman Hill to Bridgefield, St. Thomas – road reconstruction; section closed
- Highway 1C/Hope Road, St. Lucy – road reconstruction
- Highway B2, St. Andrew – drainage & gabion construction
- Highway C, Orange Hill – road rehabilitation
- Highway D, Content to Dukes, St. Thomas – road reconstruction
- Highway F Phase 1, St. John – paving & road construction
- Huntes Road, Carrington Village, St. Michael – kerb construction, mill & pave
- King’s Street, St. Andrew – gabion foundation backfilling
- Laynes Bridge, St. Joseph – culvert construction
- Mose Bottom, St. Andrew – road and drainage construction
- Philips Road, St. Joseph – milling and paving
- Prior Park, St. James – road reconstruction
- Sorrel Lane, St. Michael – road rehabilitation
- St. David’s to Coral Ridge, Christ Church – extensive pothole patching
- St. Margaret’s, St. John – kerb and culvert construction
- Station Hill, St. Peter – milling and paving
- White Hill Phase 2, St. Andrew – accommodation works
Drain Cleaning
- 3rd Ave Sion Hill, St. James
- Bawdens, St. Andrew
- Bridgefield, St. Thomas
- Crystal Heights, St. James
- Durants Village, St. James
- Edgehill Terrace, St. Thomas
- Halls Lane, Prior Park, St. James
- Halls Road, St. Michael
- Harmony Hall, Christ. Church
- Highland, St. Thomas
- Industry Road, Bank Hall, St. Michael
- Lion Castle, St. Thomas
- Pinders Ave, Culloden Road, St. Michael
- Skeetes Road, Jackmans, St. Michael
- Worthings, Christ Church

Ongoing road works
St. Michael – Work on the medium and slipper on the Mighty Grynner Highway continues, and clean-up of the area is to be completed this week. Manhole repairs and excavation also continue on the Mighty Grynner Highway. Repairs to a head wall in Martindales Road and outside The St. Michael School are ongoing. Repairs to a manhole in Tweedside Road are ongoing. Slipper and kerb repair in Clapham is presently on hold.
St. George – Masonry work will be carried out in Church Bottom. Weeding is being done in Walker’s Development while debushing is scheduled at Paradise and St. Helen’s. Drainage work is also scheduled for St. Luke’s and Charles Rowe Bridge. Pothole patching will be done in Applewaites, Paradise Road and Belair, and Valley Road.
Christ Church – In Parish Land, repairs are ongoing to a retaining kerb wall, while in 5th Avenue Crystal Crescent, Kingsland, repairs to a manhole and grill cover are being done. A. Debushing is planned for the Kendal Hill near the Edwy Talma Roundabout and Silver Sands. Pothole patching is scheduled for Vauxhall, Gibbons Main Road, Warners Main Road, Kendal Hill, Kingsland, Long Beach, Pilgrim Road, Sargeants Village, Elizabeth Park, and Thornbury Hill.
St. Philip – Excavating, compacting, road widening, and slipper and kerb construction are ongoing in Johnson Development. Mechanical debushing will be done along Church Village to Three Houses and Union to Sandy Hill. Pothole patching to be done on Highway 5 from Marley Vale to Four Square.
St. Lucy – Concrete works are scheduled for Sutherland Hill and Alexandria, and drain cleaning will be carried out in Benthams. Pothole patching is scheduled for Pie Corner, Content, and Cave Hill.
St. Peter – Repairs are ongoing to a culvert at the junction of KNR Husbands Highway and Farm Tenantry Road. Work continues on the box drain and slipper and kerb along Maynards Retreat Road. Pothole patching is scheduled for Mount Brevitor, The Mount, and The Rock. Farm Bridge remains closed until further notice. Access to the Ronald Mapp Highway from Speightstown, and vice versa, is through Warleigh Road.
St. James – Repairs are ongoing to two box drains in Porters Road. The slipper drain in Holetown is also being repaired. Pothole patching will be done in Prospect, Holders Hill, West Terrace, and Mullins Road.
St. John – Masonry works continue in Consett Bay. Weeding will be carried out in Coach Hill, and debushing will be done at Clifton Hall and Bath Depot. Pothole patching is scheduled for Massiah Street, Rosegate, Guinea, and Clifton Hall.
St. Thomas – Repairs to a dip in the road are ongoing in Mount Wilton between Laynes Bridge Junction, Straughans Village, and Mount Wilton Main Road. The footpath and retaining wall were completed at Stoney Gully, and preparation for paving has started. Debushing, drainage work, and extensive pothole patching are scheduled throughout the districts.
St. Joseph/St. Andrew – Road repairs and road works are ongoing in Coconut Grove and Newton Crescent. Construction of the concrete drain at Tent Bay and the slipper and kerb in Lakes Village continues. Road construction is ongoing at Swanns. In Springfield, the construction of a spirolite pipe culvert continues. Debushing, patching, and extensive pothole patching, and drainage work are scheduled throughout the parishes. Persons are reminded not to drive on Swanns Bridge, which has been closed due to deterioration.